City of DeKalb
HLR's surveyors began by conducting topographic and stream surveys of the Kishwaukee River and potential sites for the bike path alignment. Coordinating with both the City of DeKalb and the DeKalb Park District was essential to determine the optimal location for the proposed bike path, taking into account minimizing tree and wetland impacts.
The bike path's placement was also influenced by fill within the regulatory floodway of the Kishwaukee River. Upstream residences from the Union Pacific and Illinois Route 38 bridge crossings of the Kishwaukee are susceptible to flooding. Our design engineers developed an iterative path location that balanced compensatory storage and riverine conveyance, ensuring that the water surface upstream would not rise significantly during various storm events. Our stormwater engineers utilized HEC-RAS hydraulic modeling to verify that the proposed crossing would not pose a risk to the flood-prone buildings.
HLR also designed an overhead structure above the planned bike path to deflect any loose ballast that could fall from the railroad bridge. This posed a challenge as the design needed to be sufficiently rigid to withstand wind loading between the long pier lengths. The overhead structure also had to be positioned at least 2 feet below the bottom of the railroad bridge and above the Kishwaukee River's base flood (100-year) elevation.
Once the location was determined, the design phase began, and the properties required for easements or permanent acquisition were identified, initiating the land acquisition process. In addition to designing the bike path, which included 1,850 feet of HMA path and 250 feet of concrete path, as well as minor drainage improvements, a Railroad Protective Cover structure was designed to safeguard the path beneath the Union Pacific Railroad Bridge. Both Phase I and Phase II engineering processes were coordinated through IDOT District 3 Bureau of Local Roads and Streets.
Our professional land surveyors prepared all plats and legal descriptions for the necessary right-of-way to construct the proposed bike path. Our team also conducted appraisals and negotiations for the two parcels where right-of-way acquisition was required.
HLR completed a wetland delineation and report and obtained USACE wetland permits. Additionally, a Preliminary Environmental Site Assessment (PESA) and tree survey were conducted.
Coordination was essential to obtain approvals and permits from the following entities:
SPRINGFIELD
3085 Stevenson Dr., Ste. 201
Springfield, IL 62703
P: 217.546.3400